    Q.4: 4 men and 6 women complete a task in 24 days. If the women are at least half as efficient as the men, but not more efficient than the men, what is the range of the number of days for 6 women and 2 men to complete the same task?
    1. 30 to 33.6 days
    2. 32 to 35 days
    3. 33.6 to 35 days
    4. 30 to 35 days

 

  • Correct Answer
    Choice A. 30 to 33.6 days

Detailed Solution

4m and 6w finish in 24 days.
In one day, 4m + 6w = of task.

In these questions, just substitute extreme values to get the whole range
If a woman is half as efficient as man
4m + 3m = , 7m = , m =
6w + 2m = 3m + 2m = 5m, 5m will take days = 33.6 days

If a woman is as efficient as a man
4m + 6w finish in 24 days
10m finish of task in a day
6w + 2m = 8m, 8m will take = 30 days to finish the task.

So, the range = 30 to 33.6 days. The new team will take 30 to 33.6 days to finish the task. Choice (A)

Correct Answer: 30 to 33.6 days



Our Online Course, Now on Google Playstore!

2IIM's App

Fully Functional Course on Mobile

All features of the online course, including the classes, discussion board, quizes and more, on a mobile platform.


Cache Content for Offline Viewing

Download videos onto your mobile so you can learn on the fly, even when the network gets choppy!

Get it on Google Play

More questions from Pipes Cisterns, Work Time

  1. Fill pipes and drain pipes
  2. Three Pipes
  3. Three Pipes
  4. Work Time
  5. Fill pipes and drain pipes
  6. Pipes Cisterns - Algebra
Mathematicians are creatures of habit. This topic has been called Pipes and Cisterns because someone named it like it long ago. Pipes and Tanks would be much better - at least makes it sound like wartime.