The question is from the topic Time and distance. This question tests our understanding of relationship between time and speed when the distance is constant. It is a classic question involving the concept of speed, distance and time. Time Speed and Distance is a favorite in CAT Exam, and appears more often than expected in the CAT Quantitative Aptitude section in the CAT Exam.

Question 5: Mr. X decides to travel from Delhi to Gurgaon at a uniform speed and decides to reach Gurgaon after T hr. After 30 km, there is some engine malfunction and the speed of the car becomes \\frac{4}{5}\\)th of the original speed. So, he travels the rest of the distance at a constant speed \\frac{4}{5}\\)th of the original speed and reaches Gurgaon 45 minutes late. Had the same thing happened after he travelled 48 km, he would have reached only 36 minutes late. What is the distance between Delhi and Gurgaon?

  1. 90 km
  2. 120 km
  3. 20 km
  4. 40 km


Video Explanation


Best CAT Coaching in Chennai


CAT Coaching in Chennai - CAT 2022
Limited Seats Available - Register Now!


Explanatory Answer

Method of solving this CAT Question from Time Speed Distance: How time is related to speed?
Speed Time Distance: CAT time and distance Question 5

Let the distance from Delhi to Gurgaon be โ€˜dโ€™ km.
The first 30 km he travels at his usual speed. However, the remaining โ€˜d-30โ€™ km he travels at a reduced speed.

To travel โ€˜dโ€™ km he usually takes T hr. Therefore, to travel โ€˜d - 30โ€™ km he should ideally take \\frac{(dโˆ’30)T}{d}\\) hr. However, this is only if he travels at his usual speed. It is given that he traveled only at \\frac{4}{5}\\)th of his usual speed. Because of this he would have taken \\frac{5}{4}\\)th of the time to travel the remaining distance, i.e., he takes \\frac{1}{4}\\)th of the time extra. This is given to be 45 minutes (or \\frac{3}{4}\\)th hr)
\\frac{1}{4}\\)\\frac{(dโˆ’30)T}{d}\\) = \\frac{3}{4}\\)ย ย ย ย ย ........(1)

On the other hand, had the same thing happened after he travelled 48 km, he would have reached only 36 minutes or 34 hrs late. Hence,
\\frac{1}{4}\\)\\frac{(dโˆ’48)T}{d}\\) = \\frac{3}{5}\\)ย ย ย ย ย ........(2)

Dividing (1) by (2) and solving for d, we get d = 120 km.

The question is What is the distance between Delhi and Gurgaon? we get d = 120 km.

Hence, the answer is d = 120 km.

Choice B is the correct answer.

ย 

Best CAT Online Coaching
Try upto 40 hours for free
Learn from the best!

โ˜… Sign up Now!

Download comprehensive PDFs of past yearsโ€™ question papers with answers.

โ˜… Click here


CAT Preparation Online | CAT Arithmetic Videos On YouTube


Other useful sources for Arithmetic Question | Time Speed Distance and Races Sample Questions


CAT Questions | CAT Quantitative Aptitude

CAT Questions | CAT DILR

CAT Questions | Verbal Ability for CAT


Where is 2IIM located?

2IIM Online CAT Coaching
A Fermat Education Initiative,
19/43, MG Chakrapani St,
Sathya Garden, Saligramam, Chennai 600 093

How to reach 2IIM?

Mobile: (91) 99626 48484
WhatsApp: WhatsApp Now
Email: info@2iim.com