The question is from the topic Relative Speed. This is a classic CAT level question testing your understanding in the concept of relative speed from Time Speed and Distance. Time Speed and Distance is a favorite in CAT Exam and appears more often than expected in the CAT Quantitative Aptitude section in the CAT Exam

Question 27 : Two trains left from two stations P and Q towards station Q and station P respectively. 3 hours after they met, they were 675 Km apart. First train arrived at its destination 16 hours after their meeting and the second train arrived at its destination 25 hours after their meeting. How long did it take for the first train to make the whole trip?

  1. 18h
  2. 36h
  3. 25h
  4. 48h



Best CAT Coaching in Chennai


CAT Coaching in Chennai - CAT 2022
Limited Seats Available - Register Now!


Explanatory Answer

Method of solving this CAT Question from Time Speed Distance: Let's start with creating a visual of how the trains cross each other.
Speed Time Distance: CAT time and distance Question Relative speed

Total distance travelled by both the trains before meeting = D. This distance will be covered in the proportion of their speeds. Clarify with the diagram.

3 hours after meeting distance travelled by A = SA * 3 and by B = SB * 3
Therefore, 3 (SA + SB) = 675 => SA + SB = 225.

Now the remaining distance to be covered by first train is DSB/(SA + SB)
Therefore, time taken = \\frac{DS_{B}}{(S_{A} + S_{B})S_{A}}\\) = 16 --------- (1)
Similarly, \\frac{DS_{A}}{(S_{A} + S_{B})S_{A}}\\) = 25 --------- (2)

Dividing equation 1 by 2 -

\\frac{S_A^2}{S_B^2}\\) = \\frac{25}{16}\\) => \\frac{S_A}{S_B}\\) = \\frac{5}{4}\\).
Therefore, SA + \\frac{4}{5}\\) * SA = 225
=> SA = 125 Km/hr and SB = 100 Km/hr
From equation 2, \\frac{D}{S_A}\\) = 16 * \\frac{225}{100}\\) = 36h,
which is the time taken for the first train to complete the journey.

The question is "How long did it take for the first train to make the whole trip?"

Hence,it took 36h for the first train to make the whole trip.

Choice B is the correct answer.

ย 

Best CAT Online Coaching
Try upto 40 hours for free
Learn from the best!

โ˜… Sign up Now!

Download comprehensive PDFs of past yearsโ€™ question papers with answers.

โ˜… Click here


CAT Preparation Online | CAT Arithmetic Videos On YouTube


Other useful sources for Arithmetic Question | Time Speed Distance and Races Sample Questions


CAT Questions | CAT Quantitative Aptitude

CAT Questions | CAT DILR

CAT Questions | Verbal Ability for CAT


Where is 2IIM located?

2IIM Online CAT Coaching
A Fermat Education Initiative,
19/43, MG Chakrapani St,
Sathya Garden, Saligramam, Chennai 600 093

How to reach 2IIM?

Mobile: (91) 99626 48484
WhatsApp: WhatsApp Now
Email: info@2iim.com