Question 15 :A bus starts from a bus stop P and goes to another bus stop Q. In between P and Q, there is a bridge AB of certain length. A man is standing at a point C on the bridge such that AC:CB = 1:3. When the bus starts at P and if the man starts running towards A, he will meet the bus at A. But if he runs towards B, the bus will overtake him at B. Which of the following is true?

  1. Bus travels 3x times faster than the man
  2. Bus travels 2x times faster than the man
  3. The bus and the man travel at the same speed
  4. 4x the speed of the man is equal to 3x the speed of the bus



Best CAT Coaching in Chennai


CAT Coaching in Chennai - CAT 2022
Limited Seats Available - Register Now!


Explanatory Answer

Method of solving this CAT Question from Time Speed Distance: Think about the time taken by the bus and the man! That will tell you what their speeds are related to!
CAT Speed Time Distance: Races Question involving Relative Speed Bridges

Let the speed of the bus be โ€˜bโ€™ and man be โ€˜mโ€™.
Let the distance between P and A be y.
AC:CB = 1:3 implies AC = x and CB = 3x

When bus goes from P to A and the man from C to A, time taken by both are equal and they meet at A.
y/b = x/m or
b/m = y/x --- (1)

When bus goes from P to B and the man from C to B, again time taken by both are equal and they meet at B.
(y+x+3x)/b = 3x/m
b/m = (4x+y)/3x ---(2)

Equating (1) and (2), we get y/x = (4x+y)/3x
3y = 4x + y or y = 2x

Therefore ratio of speeds b/m = 2x/x or 2 : 1

The question is "When the bus starts at P and if the man starts running towards A, he will meet the bus at A. But if he runs towards B, the bus will overtake him at B. Which of the following is true?"

Hence, the Bus travels 2x times faster than the man.

Choice B is the correct answer.

ย 

Best CAT Online Coaching
Try upto 40 hours for free
Learn from the best!

โ˜… Sign up Now!

Download comprehensive PDFs of past yearsโ€™ question papers with answers.

โ˜… Click here


CAT Preparation Online | CAT Arithmetic Videos On YouTube


Other useful sources for Arithmetic Question | Time Speed Distance and Races Sample Questions


CAT Questions | CAT Quantitative Aptitude

CAT Questions | CAT DILR

CAT Questions | Verbal Ability for CAT


Where is 2IIM located?

2IIM Online CAT Coaching
A Fermat Education Initiative,
19/43, MG Chakrapani St,
Sathya Garden, Saligramam, Chennai 600 093

How to reach 2IIM?

Mobile: (91) 99626 48484
WhatsApp: WhatsApp Now
Email: info@2iim.com